Searenergy Wins Hook-Up Contract for Bałtyk Offshore Wind Farms
Searenergy Poland has been selected by the Equinor-Polenergia joint venture to perform hook-up and commissioning for the 1.44 GW Bałtyk 2 and Bałtyk 3 offshore wind farms, which will power over two million Polish homes from 2027.

Searenergy Poland has secured the contract to perform hook-up and commissioning for the Bałtyk 2 and Bałtyk 3 offshore wind farms. The company was selected by the joint venture between Equinor and Polenergia for work that will see first power delivered in 2027.
The contract covers the critical hook-up and commissioning of both offshore substations. It also includes commissioning support for up to 100 wind turbines during the construction phase. Full commercial operation for the projects is planned for 2028.
Project geography and scale
The two fixed-bottom wind farms are located off Poland’s northern coast in the Baltic Sea. Bałtyk 2 sits approximately 37 kilometres from shore, while Bałtyk 3 is about 22 kilometres out.
Each project has a planned capacity of 720 MW. Together, they will form a 1.44 GW complex designed to supply renewable electricity to more than two million Polish households.
| Project | Distance from Coast | Capacity |
|---|---|---|
| Bałtyk 2 | 37 km | 720 MW |
| Bałtyk 3 | 22 km | 720 MW |
Construction timeline and milestones
Major installation work is already complete. In September 2026, Heerema Marine Contractors finished a four-month campaign to install all 100 wind turbine foundations and the two substation jacket foundations. The company used its semi-submersible crane vessel Thialf for the work.
Heerema is scheduled to return to the Baltic Sea this winter to install the offshore substation topside for Bałtyk 2. The topside for the Bałtyk 3 substation is slated for installation in the summer of 2027. Each project will feature 50 Siemens Gamesa wind turbines, each with a 14.4 MW rating.
Searenergy’s role and expertise
Based in Gdynia, Searenergy Poland will deliver engineering, health, safety and environment services, and on-site procurement during construction. The company will supply key commissioning personnel for both onshore and offshore activities. Teams from both its Gdynia and Hamburg offices will be involved.
Searenergy managing director Natalia Kress stated that the company's core business is platform commissioning and asset maintenance. "The commissioning of platforms and the maintenance of assets are at the core of Searenergy’s business," Kress said.
Following the construction phase, Searenergy will also carry out corrective maintenance on the wind turbines' transition pieces. This work will be conducted from the developers’ operations and maintenance base in Łeba. The first electricity from the two wind farms is expected to flow in 2027.