Fram Wind Solutions secures $209m for floating wind project
Fram Wind Solutions has received a $209 million state grant to build a 37MW floating wind farm off Norway, aiming to prove the technology's commercial viability.

Fram Wind Solutions has received Nkr1.94bn ($209m) from the state-owned enterprise Enova. The funding will support a 37MW floating wind project at the METCentre demonstration site off Karmøy, Norway. The grant is contingent on the developer meeting several conditions, including reaching a final investment decision, securing finance, and entering supplier agreements within the next 24 months.
Fram Wind Solutions is a partnership between BW Offshore, Fram Green Technology, and Grieg Kapital. The project will add two 18.5MW floating wind turbines to the test centre. This development is part of a broader push to advance floating offshore wind technology, which is critical for harnessing renewable energy in deep-water areas.
Project specifications and technology
The project will deploy two 18.5MW turbines mounted on BW Ideol's Damping Pool floating foundations. This patented foundation design aims to reduce construction, installation, and operational costs for floating wind. The installation is expected to generate approximately 300GWh of electricity annually. That output is equivalent to the yearly power consumption of around 15,000 Norwegian households.
The technology has a track record in other demonstration projects. BW Ideol's Damping Pool system is already in use at the 30MW EolMed floating wind farm off the French Mediterranean coast. That farm first supplied power to the grid in April 2026 and reached full capacity with three 10MW turbines the following month.
Funding context and criteria
The grant to Fram Wind Solutions is part of a larger Nkr3.94bn ($430m) allocation from Enova for two floating wind projects at the METCentre. The other recipient is Fortius Offshore Wind, which received Nkr2bn for its own two-turbine project. Together, the initiatives will add 74MW of new floating wind capacity.
Enova, which operates under the Norwegian Ministry of Climate and Environment, awards funding based on specific criteria. These include projected energy output per funding unit, the potential for broader technology adoption, carbon footprint, biodiversity impact, and prospects for cost reduction.
Project timeline and commercial goals
The primary goal of the Fram Wind Solutions project is to demonstrate the commercial viability of floating offshore wind and drive down its costs. Developers aim to install the turbines and begin energy production within the next five years. The five-year timeline is set to deliver energy equivalent to powering 15,000 households annually.
The ownership structure of the venture is clear. BW Offshore holds a 50% stake in Fram Wind Solutions, while Grieg Kapital owns 35% and Fram Green Technology holds 15%. Also, BW Offshore maintains a 68% ownership stake in the technology provider, BW Ideol. Developers aim to install the turbines within the next five years.